Commercial Office Fit-Out - Battersea Power Station, London

Client: Main Contractor/Global Technology Company

Services: CxC

This project involved a high-specification Category B fitout covering approximately 500,000 sq. ft. for the London headquarters of a global technology company in Battersea. The objective was to create a state-of-the-art workplace incorporating advanced building systems, sustainable design, and employee well-being initiatives.

The project spanned multiple floors, each serving a distinct function:

  • Level 11 – Roof plant area

  • Level 10 – Executive floor

  • Levels 6 to 9 – General offices

  • Level 5 – Meeting rooms and kitchen area

  • Upper Ground Floor (UGF) – Reception area

Key aspects of the fitout included:

  • Installation of communication rooms forming part of the critical path

  • Chilled ceilings and Under Floor Air Distribution (UFAD) for efficient climate control

  • A dedicated UPS system ensuring critical power supply to essential areas

  • Compliance with BREEAM Outstanding and WELL Platinum certification standards

  • Seasonal commissioning and a 12-month defects attendance period post practical completion

  • Daily management of trade contractors to ensure smooth workflow and accountability

  • Independent monitoring of the commissioning process to maintain quality standards

  • Independent management of the commissioning programme, including workshops with trade contractors for complex handovers

  • Organisation and effective communications to facilitate coordination and problem-solving

  • Delivery of optimised and efficient systems for sustainability and operational excellence

  • Ensuring successful handover of all critical life services to the client at the point of use

  • Achieving optimal synergy with trades to successfully deliver Excellent and Platinum environmental standards for BREEAM and WELL accreditations

  • Delivering a complex natural ventilation strategy to enhance sustainability and occupant comfort

  • Navigating issues in real time to avert delays before they impact project timelines

 

Challenges and Solutions:

  1. Stringent Sustainability Goals:

    • Challenge: Achieving BREEAM Outstanding and WELL Platinum required rigorous sustainability measures.

    • Solution: Integrated energy-efficient systems, optimized air quality solutions, and implemented smart building technologies.

  2. Critical Path Management:

    • Challenge: Communication rooms were on the critical path, requiring precise coordination.

    • Solution: A structured commissioning strategy ensured early completion and risk mitigation.

  3. Seamless Integration of Mechanical and Electrical Systems:

    • Challenge: Installing chilled ceilings and UFAD while maintaining operational efficiency.

    • Solution: Conducted phased testing and commissioning to ensure optimal performance before handover.

  4. Long-Term Performance Monitoring:

    • Challenge: Ensuring continued system performance after completion.

    • Solution: Implemented seasonal commissioning and a structured 12-month defect monitoring strategy.

Conclusion: This project exemplifies the integration of advanced workplace infrastructure, sustainability, and technical excellence in large-scale office fitouts. By successfully managing complex building systems and adhering to strict certification standards, the project delivered a future-ready, sustainable, and high-performance workplace for the global technology company in London.