Commercial Office Fit-Out - Battersea Power Station, London
Client: Main Contractor/Global Technology Company
Services: CxC
This project involved a high-specification Category B fitout covering approximately 500,000 sq. ft. for the London headquarters of a global technology company in Battersea. The objective was to create a state-of-the-art workplace incorporating advanced building systems, sustainable design, and employee well-being initiatives.
The project spanned multiple floors, each serving a distinct function:
Level 11 – Roof plant area
Level 10 – Executive floor
Levels 6 to 9 – General offices
Level 5 – Meeting rooms and kitchen area
Upper Ground Floor (UGF) – Reception area
Key aspects of the fitout included:
Installation of communication rooms forming part of the critical path
Chilled ceilings and Under Floor Air Distribution (UFAD) for efficient climate control
A dedicated UPS system ensuring critical power supply to essential areas
Compliance with BREEAM Outstanding and WELL Platinum certification standards
Seasonal commissioning and a 12-month defects attendance period post practical completion
Daily management of trade contractors to ensure smooth workflow and accountability
Independent monitoring of the commissioning process to maintain quality standards
Independent management of the commissioning programme, including workshops with trade contractors for complex handovers
Organisation and effective communications to facilitate coordination and problem-solving
Delivery of optimised and efficient systems for sustainability and operational excellence
Ensuring successful handover of all critical life services to the client at the point of use
Achieving optimal synergy with trades to successfully deliver Excellent and Platinum environmental standards for BREEAM and WELL accreditations
Delivering a complex natural ventilation strategy to enhance sustainability and occupant comfort
Navigating issues in real time to avert delays before they impact project timelines
Challenges and Solutions:
Stringent Sustainability Goals:
Challenge: Achieving BREEAM Outstanding and WELL Platinum required rigorous sustainability measures.
Solution: Integrated energy-efficient systems, optimized air quality solutions, and implemented smart building technologies.
Critical Path Management:
Challenge: Communication rooms were on the critical path, requiring precise coordination.
Solution: A structured commissioning strategy ensured early completion and risk mitigation.
Seamless Integration of Mechanical and Electrical Systems:
Challenge: Installing chilled ceilings and UFAD while maintaining operational efficiency.
Solution: Conducted phased testing and commissioning to ensure optimal performance before handover.
Long-Term Performance Monitoring:
Challenge: Ensuring continued system performance after completion.
Solution: Implemented seasonal commissioning and a structured 12-month defect monitoring strategy.
Conclusion: This project exemplifies the integration of advanced workplace infrastructure, sustainability, and technical excellence in large-scale office fitouts. By successfully managing complex building systems and adhering to strict certification standards, the project delivered a future-ready, sustainable, and high-performance workplace for the global technology company in London.